Mortar Estimator – Bags & Volume for Brick, Block & Stone
Total mortar volume
—
Assumes 3/8 inch joints (10 mm metric) unless you change the joint thickness. Bag yields: 80 lb = 0.7 cu ft, 60 lb = 0.5 cu ft, 40 lb = 0.35 cu ft, 25 kg = 0.015 m³, 50 kg = 0.030 m³. Bag counts are rounded up and the waste allowance is applied before bag counts. Stone estimation is approximate.
What Is a Mortar Estimator?
A mortar estimator tells you how much mortar you need to lay a given area of brick, block or stone before you open the first bag. Running short mid-wall means a cold joint and a trip to the supplier. Mixing too much means a wheelbarrow of set mortar you paid for and cannot use. For any wall larger than a few square feet, guessing bag counts by eye gets expensive fast.
This tool converts either the wall area or a straight unit count into a total mortar volume in cubic feet or cubic meters, then breaks it down into the bag counts for the standard sack sizes (80, 60 and 40 lb, or 25 and 50 kg), the total weight you will be lifting, an optional units-needed figure so you can order brick or block at the same time, and a cost estimate from the price per bag. The joint-thickness field adjusts the output when you are working to a joint width other than the standard 3/8 inch.
How to Use This Mortar Estimator
- Choose your unit system. The Imperial and Metric buttons at the top of the tool relabel every field and unit badge at once. Switching also clears the dimension boxes so you cannot mix feet into a meters calculation.
- Pick the masonry type. Brick, 8 inch Block, 6 inch Block or Stone. This choice controls both the mortar-per-unit constant and the coverage per unit that drives the units-needed figure.
- Choose how you want to enter the job. By Area takes a wall length and height. By Count takes the number of bricks or blocks directly and is the more precise method when you already have a purchase list.
- Set the joint thickness if it differs from 3/8 inch. The tool scales the mortar volume linearly with joint width. Leave the field blank to use the standard 3/8 inch (10 mm metric) default.
- Adjust the waste allowance. The dropdown defaults to 10 percent, which suits most walls. Choose 0 percent for the raw geometric figure, or 15 to 20 percent for rough stone and irregular coursing.
- Add a price for a cost estimate. Enter the price per bag, pick a currency, and a cost card appears in the results alongside the bag counts. Everything recalculates as you type, and the Reset button clears the form.
The Formulas Behind the Numbers
Every mode uses the same core relationship: mortar volume equals the number of masonry units times the mortar per unit, adjusted for joint thickness and then for waste.
By Area: Units = (Length × Height) ÷ Coverage per unit. Mortar volume = Units × Mortar per unit.
By Count: Mortar volume = Number of units × Mortar per unit.
Joint adjustment: Adjusted mortar = Base mortar × (Joint thickness ÷ 3/8 inch). The relationship is treated as linear, which matches practice for joints between 1/4 inch and 1/2 inch.
Waste allowance: Final volume = Adjusted mortar × (1 + Waste % ÷ 100).
Bag count: Bags = Final volume ÷ Bag yield, always rounded up. In imperial mode that means cubic feet divided by 0.7 (for an 80 lb bag). In metric mode that means cubic meters divided by 0.015 (for a 25 kg bag).
Mortar Yields and Coverage at a Glance
These are the fixed numbers the calculator relies on. Coverage figures assume a single wythe (one-unit-thick) wall and standard 3/8 inch joints.
| Masonry type | Mortar per unit | Units per sq ft | 1 bag covers approx. |
|---|---|---|---|
| Modular brick | 0.020 cu ft | 6.86 bricks | 35 bricks |
| 8 inch CMU block | 0.045 cu ft | 1.05 blocks | 16 blocks |
| 6 inch CMU block | 0.030 cu ft | 1.05 blocks | 23 blocks |
| Rough stone (approx.) | 0.150 cu ft | 1.00 sq ft | 5 sq ft |
Values assume an 80 lb bag of mortar mix at 0.7 cu ft yield, single wythe, and 3/8 inch joints. Real coverage varies with masonry unit size, joint width, bedding depth and site conditions.
Worked Examples
Example 1: A 20 ft × 8 ft brick wall at default settings
The default setting in the tool is a brick wall by area with 3/8 inch joints and 10 percent waste. Entering 20 ft by 8 ft gives a wall area of 160 sq ft. Dividing by 0.146 sq ft per brick gives about 1,096 bricks. That is 1,096 × 0.02 = 21.92 cu ft of mortar, which becomes 24.1 cu ft after the 10 percent waste allowance. At 0.7 cu ft per 80 lb bag that is 34.5, rounded up to 35 bags of 80 lb mortar, or roughly 2,800 lb of material.
Example 2: An 8 inch block wall by unit count
Laying 200 standard 8 inch CMU blocks. Using the by-count method with 3/8 inch joints and 10 percent waste, the base mortar volume is 200 × 0.045 = 9.0 cu ft. With waste that becomes 9.9 cu ft. That is 9.9 ÷ 0.7 = 14.1, rounded up to 15 bags of 80 lb mortar, or about 1,200 lb of material.
Example 3: A rough stone wall, 30 ft × 6 ft
A 30 ft by 6 ft stone wall is 180 sq ft of face. Using the stone constants with 15 percent waste, the base volume is 180 × 0.15 = 27 cu ft. Adding 15 percent gives 31.05 cu ft. That is 31.05 ÷ 0.7 = 44.4, rounded up to 45 bags of 80 lb. Stone coverage varies far more than brick or block, so the 20 percent waste option is safer for rough rubble.
Switching to metric mode with a 6 m × 2.5 m brick wall at 10 mm joints and 10 percent waste gives a wall area of 15 m². At 0.01356 m² per brick that is about 1,106 bricks, or 0.63 m³ of mortar. With waste that becomes 0.69 m³, which is 46 bags of 25 kg mortar.
Five Mortar Mistakes That Cost Money
- Using the wrong mortar type for the wrong job. Type N is the general-purpose above-grade mix. Type S is stronger and suits below-grade and high-wind zones. Type M is only for severe exposure. Using Type M everywhere wastes money, and using Type O for structural work is unsafe.
- Wetting brick that is already saturated. Very dry brick pulls water out of the mortar before it can cure, causing weak joints. Very wet brick stops the mortar from sticking. Aim for saturated-surface-dry, not soaked and not bone dry.
- Mixing too much mortar at once. Mortar starts to set within 1.5 to 2 hours. Mixing a full wheelbarrow for a small wall leaves you dumping half of it. Mix in batches sized to what you can lay in 90 minutes.
- Ignoring the joint profile. Concave and V-joints shed water and last decades. Raked or flush joints on exterior walls let water in and fail within a few winters. Always finish the joint with a tool, never a trowel edge.
- Forgetting that mortar also bonds the second wythe. Cavity walls, double-brick walls and any wall with a header course use far more mortar than a single wythe calculation suggests. If your wall is more than one unit thick, multiply the mortar volume by the number of wythes and add reinforcement ties.
Frequently Asked Questions
How much mortar do I need for 100 bricks?
About 2 cubic feet of mortar for 100 modular bricks with standard 3/8 inch joints. That is roughly 3 bags of 80 lb mortar mix once a 10 percent waste allowance is included.
How many bricks will one bag of mortar cover?
One 80 lb bag of mortar mix yields about 0.7 cubic feet, which covers approximately 35 modular bricks with 3/8 inch joints. Larger bricks or wider joints reduce the coverage.
What is the difference between mortar and concrete?
Mortar is a mix of cement, lime and sand used to bond masonry units. Concrete adds coarse gravel aggregate and is used for structural pours like slabs, footings and columns.
What is the difference between Type N and Type S mortar?
Type N is a medium-strength general-purpose mix for above-grade walls. Type S is stronger and more water-resistant, making it the choice for foundations, retaining walls and areas with high wind loads.
Do I need a different mortar for block versus brick?
No, Type N or Type S mortar works for both block and brick. The difference is in the mix ratios you buy and the mortar per unit, since a block face is much larger than a brick face.
Can I use thinset instead of mortar for a brick wall?
Thinset is designed for tile and thin veneer, not structural brickwork. Standard brick and block walls need a sand-cement mortar with a bed joint thick enough to level each course, which thinset cannot provide.
How much does a bag of mortar cost?
An 80 lb bag of preblended mortar typically costs between 10 and 20 dollars depending on region and mortar type. Buying sand and cement separately is cheaper for large jobs but slower on site.
How long does mortar take to set before I can lay the next course?
Mortar is firm enough to support the next course within about 20 to 30 minutes in normal conditions. Let the wall cure for 24 hours before applying heavy load or backfilling against it.